Aureos rises to Highland engineering challenge
Company News | 18 Nov 2026
Aureos colleagues overcame difficult terrain, stormy weather and the challenges of working alongside a historic railway viaduct to deliver a vital access solution for Network Rail's £13m West Highland Line improvement programme.
Set amid the spectacular scenery of the Scottish Highlands, Loch nan Uamh Viaduct, also known as Glen Mama Viaduct, has carried trains between Fort William and Mallaig since 1901.

When Network Rail planned track renewal at the viaduct as part of its latest investment programme, Aureos was asked to provide temporary access to the structure ahead of a nine-day railway closure in November.
But what initially appeared to be a relatively straightforward requirement soon became a challenging engineering project.
Finding a safer solution
During an initial site visit, Aureos Construction Manager Leon O'Connor identified problems with Network Rail's proposed modular staircase arrangement.
The uneven terrain, comprising peat and exposed rock, meant the stairs could only be installed in short sections, leaving operatives to negotiate potentially slippery ground between them.
Leon proposed an alternative: a bespoke scaffold staircase positioned alongside one of the viaduct's central piers.
However, the structure's Category B listed status meant conventional scaffold fixings could not be drilled into the historic concrete.
Instead, Aureos developed a solution incorporating kentledge, using carefully calculated additional weight to stabilise the scaffold without damaging the viaduct.
Specialist engineering expertise
The project brought together Aureos' construction team, ATSL's specialist engineering expertise and our supply chain.
ATSL designed the temporary works foundation and undertook the Category 3 independent check of the scaffold design. Aureos colleagues Raymond Guam and Will Goldsworthy contributed to the temporary works engineering.
Ground investigations, detailed designs and Network Rail approvals were also required before construction could begin.
The completed scaffold provided access at a height of 13.1m, with its design accounting for wind loading, ground-bearing pressures and structural stability.
Racing against the weather
With Network Rail's blockade approaching, the team faced an unexpected setback.
Storms and high winds prevented the planned installation during the week commencing 24 October, leaving just one week to complete the scaffold before the railway works began.
Leon, who also acted as Temporary Works Coordinator, managed the various specialists and contractors involved.
He said: "The challenge was providing safe access across difficult ground without compromising a listed structure. There was a lot of engineering involved, particularly around the foundation and scaffold design.
"Then the weather took a week out of our programme, which certainly focused everyone's minds! Everyone pulled together to get the job done safely and on time."
Despite the disruption, the scaffold was successfully completed and handed over to Network Rail on schedule.
Protecting railway heritage
The viaduct itself has a remarkable history. Completed in 1901, the eight-arch concrete structure is reputed to contain the remains of a horse and cart that fell into one of its piers during construction. Specialist scanning in 2001 confirmed their presence, more than a century after the accident.
Today, the viaduct remains an important part of the West Highland Line, with Network Rail's £13m programme including more than 4km of track renewal and other improvements across the route.
Aureos will continue supporting temporary works inspections before eventually removing the scaffold and reinstating the ground.
For our colleagues, the project demonstrates how practical experience, specialist engineering expertise and teamwork can overcome demanding challenges, helping maintain railway infrastructure that has served communities for generations.